Infrastructure Services Projects
Roads are a major focus for Athabasca County and each year it is the greatest single expenditure for the municipality.The overall investment in roads for 2020 is just over $11 million. Grants account for just over $3.3 million of the total. The County continues to cost-share for dust control applications at a cost of $477,624 to the municipality. The 2020 Budget includes the following:
- Road Grading $4.1 million
- Road Graveling $2.4 million
- Bridge repairs $550,000
- Right of Way maintenance $675,000
- Road Maintenance $508,800
- Hard Surfacing Projects $928,000
2020 Construction Projects
By clicking on the menu below you can view the list of 2020 Road Construction projects. Included are estimated time frames for the work which can be affected by inclement weather.
Reconstruction
Division 1 – Polak Farms South/Deshamis North (2 miles) – Completed
RGE RD 225, NE 7-62-22-W4 to SE 19-62-22-W4
11 May to 8 July
Division 7 – Lega West (.5 miles) – Completed
TWP Rd 664, NE 21-66-17-W4 11
18 July to 18 July
Division 4 – Narrow Lake Access (1 mile) – Completed
TWP RD 652, NW 23-65-23-W4 to NE 23-65-23-W4 23
20 July to 7 August
Division 2 – Anderson West (1 mile) – Completed
TWP RD 650, From Hwy 827 to TWP RD 222
10 August to 27 August
Division 6 & 7 – Homeniuk East (1.5 miles)
TWP RD 680, RGE RD 184 to RGE RD 191 (Cost Share)
25 September to 20 October
Division 3 – Berube (1 mile)
TWP RD 644, RGE RD 204 to RGE RD 205
22 October to 9 November
Clay Cap – Ditching
Division 5 – Doole (220 ft)
Brushing, fencing and dugout
13 July to 16 July
Division 8 – Grosmont West (.75 miles)
1 October to 16 October
Shoulder Pulls
Division 4 – Olson Cut Across (1 mile) – Completed
13 July to 17 July
Division 1 – Northland Dairy East (1 mile) – Completed
18 July to 24 July
Division 9 – Pleasantview Extension (4 miles) – Completed
27 July to 6 August
Division 6 – Blue Jay East (2.5 miles) – Completed
7 August to 14 August
Division 6 & 7 – Homeniuk East (0.5 miles) – Completed
17 August to 20 August
Division 2 – Slaughter House Road (2.5 miles) – Completed
21 August to 29 August
Division 4 – Sunseeker Marine Road (3.5 miles) – Completed
31 August to 9 September
Division 8 – Westwind Park West (1 mile)
10 September to 30 September
Division 3 – Lamoureux West (1 mile)
5 October to 8 October
Division 7 – Atmore South (1.5 miles)
9 October to 19 October
Division 5 – Parson Road (1 mile)
20 October to 26 October
Contract
Division 7 & 8 – Ward Lake Loop (6 miles)
Start Date: 15 June
Division 9 – Sawdy West (1.5 miles)
Start Date: Held Over to Spring 2021
Division 6 – WR Lagoon Road West (0.5 miles) COMPLETE
Dust Abatement Trial
Start Date: 5 May
Division 5 – Tower Road (2 miles) COMPLETE
Dust Abatement Trial
Start Date: 5 May
Division 8 – Grosmont Road (2.1 miles) COMPLETE
Base repair, overlay, drainage repair ($800,000)
Start Date: June 5
Keep Safety in Mind
Slower speeds help to ensure the safety of both our workers and you. They also reduce the chance for damage to equipment and your vehicle.
Rocks can dislodge from the road surface when graders are working, so keep a safe following distance and pass only when it is safe to do so.
Unless otherwise posted, the speed limit on all County roads in ideal driving conditions is 80 km/h. Inclement weather can cause road surfaces to become more slippery than usual. Please drive with caution and follow the directions of all flag people in construction areas.